Page 1 of 1

Disconnecting from Project

Posted: Fri Feb 23, 2007 9:12 am
by JiriWalek
Hello, we have received strange problem in FT forum, it is more Subversive related so I copy it here.
The original topic is here: http://forums.polarion.org/viewtopic.php?t=1278

-----------------------------

Hi,

I've checked out 2 Tracker projects:
- one from open site
- one from site, which requires VPN

worked with these 2 projects without problem, then I don't need the second one (the one with VPN). I disconnected this project from SVN and deleted the project from Eclipse.

Now, I disconnect from VPN (don't need this anymore) and try to synchronize other project.
I see some files gets updated and then comes error "some resources could not be synchronized" timeout exceptions for "/repos/..." (however it's not clear which URL it tries to access)!
And my open project is not fully synchronized

Obviously FastTrack keeps connection to the repository even if there are no open projects.

If I establish VPN connection - I get successful synchronization of the remaining project.

What should I do to remove "VPN-ed" project completely out of the FastTrack sync?

Thank you in advance!
Best regards,
Nick