Notification if dueDate is exceed

Description
sk-tsb
Posts: 16
Joined: Tue Jul 17, 2018 8:23 am

Notification if dueDate is exceed

Postby sk-tsb » Thu Jul 19, 2018 5:51 am

Hello all,

is there a possibility to create some notification email if a dueDate of a work item is exceed ?


Thanks in advance,

Sven

Jürgen
Posts: 44
Joined: Tue Sep 12, 2017 1:02 pm

Re: Notification if dueDate is exceed

Postby Jürgen » Mon Jul 23, 2018 7:44 am

Hi, Sven

in the configuration settings for the notification there is a button "Advanced Settings", that allows to define the fields which are used for notification.

Jürgen

Andreas_D
Posts: 1
Joined: Wed Jul 25, 2018 5:16 am

Re: Notification if dueDate is exceed

Postby Andreas_D » Wed Jul 25, 2018 5:28 am

Hello sk-tsb,

I think there is no way the solve this with a Polarion standard feature.

We have solved the problem by writing a java script with we call by the polarion scheduler each day.
We query all Items/Tasks with due date today and send an email to the assignee.
The script run once per day.

Best Regards
Andreas

Jürgen
Posts: 44
Joined: Tue Sep 12, 2017 1:02 pm

Re: Notification if dueDate is exceed

Postby Jürgen » Thu Jul 26, 2018 10:17 am

ah, sorry...

my answer was not helpful. I thought you meant "changed", not "exceeded".

It is definitely too hot in Germany right now