Search found 6 matches

by Oliver.Meyer
Fri Mar 30, 2018 8:13 am
Forum: Polarion Application Lifecycle Management (ALM)
Topic: Calculating Priority from linked Item does not work
Replies: 6
Views: 2952

Re: Calculating Priority from linked Item does not work

I think it cannot be done. The documentation is propably right (to some extend) and the UI is crap. Documentation says: ScrShot-Help - Polarion ALM Platform - Mozilla Firefox-20180330095348.png So no "getting values from Parents." I did a test with two new fields on task, both float: value...
by Oliver.Meyer
Thu Mar 29, 2018 3:06 pm
Forum: Polarion Application Lifecycle Management (ALM)
Topic: Calculating Priority from linked Item does not work
Replies: 6
Views: 2952

Re: Calculating Priority from linked Item does not work

Thank you very much for the pointer! I read that section before. My interpretation was and is, that priority cannot be used as calculated field . But, I should be able to use it as the source for calculating another user defined field "derivedPriority". But: I could try to calculate someth...
by Oliver.Meyer
Thu Mar 29, 2018 1:33 pm
Forum: Polarion Application Lifecycle Management (ALM)
Topic: Calculating Priority from linked Item does not work
Replies: 6
Views: 2952

Re: Calculating Priority from linked Item does not work

Thanks. I tried to work around the orientation issue of the relation, by adding another calculation that gets values from the child items instead of the parent. So, I expect one of those to receive values, but no :( I attach the config files: ⋅  task-calculated-fields.xml ⋅  work...
by Oliver.Meyer
Thu Mar 29, 2018 7:55 am
Forum: Polarion Application Lifecycle Management (ALM)
Topic: Calculating Priority from linked Item does not work
Replies: 6
Views: 2952

Calculating Priority from linked Item does not work

Hi, My problem: I try to calculate the priority of a task from the priority of the requirement it implements, but I fail. What I have: I have work items of type requirements. I have work items of type task. I create relations task -implements-> requirements (Usualy multiple tasks implement one requi...
by Oliver.Meyer
Fri Jun 19, 2015 3:20 pm
Forum: Polarion Application Lifecycle Management (ALM)
Topic: Vertical Resize in Workitem View breaks display
Replies: 2
Views: 2420

Re: Vertical Resize in Workitem View breaks display

Thanks for the work around, but my real problem is another that I believe to be fixed with the vertical resize problem as well Although I rarely resize the window, I believe that this behaviour also causes the AddOn Fireguesture to not work correctly on work item pages. I use it to scroll to the top...
by Oliver.Meyer
Wed Jun 10, 2015 4:30 pm
Forum: Polarion Application Lifecycle Management (ALM)
Topic: Vertical Resize in Workitem View breaks display
Replies: 2
Views: 2420

Vertical Resize in Workitem View breaks display

Hi. If I resize the work item display in Firefox, the content of the window does not get resized. If I reduze the height the lower part of the scroll bar disappears. If I enlarge the height a white space below the scroll bar appears, but the viewable space of the work item does not increase. Does an...